We accept the challenge by understaning the importance of time given by our client with zero accident.
-
Project Type
We accept the challenge by understaning the importance of time given by our client with zero accident. -
Clients
-
Completion
Jun 15 , 2021
Bulleh Shah Packaging Pvt Limited Kasur, Punjab, Pakistan
Shutdown Job to increase factory productivity by 20% by replacing old with new equipemnt 1st foundation cutting time was given 24 hrs to DCC, but our team did it, in only 7 hours with appreciation. Total job duration was 21 days , and the job was successsfully completed before given time frame.